Posts tagged as Medupi

Medupi power station synchronises to the grid

  Eskom has announced that Unit 6 of the Medupi power station was synchronised to the national power grid at 11h03 on 2 March 2015. Synchronisation, or first power, is the process whereby the generator in the unit is electrically connected to the national power grid, in such a way that its power is aligned […]

Deadline for syncronisation of Unit 6 at Medupi delayed a further 6 weeks

  Roman Crookes, Eskom’s project manager at Medupi Power Station, advised yesterday that the deadline for synchronisation of the first unit at Medupi Power station has been extended by a further six weeks, from mid February 2015 to end March 2015. This follows the recent disclosure by Eskom that the commercial operation date for the […]

Eskom’s boiler contractor at Medupi and Kusile defends its reputation

  Eskom’s boiler works contractor at Medupi and Kusile has moved to defend its reputation, and to clarify its position in respect of any perceived non-performances in meeting its contractual obligations to deliver steam of the right cleanliness, speed, temperature, pressure and mass flow-rate to the turbines at the power station construction sites. At a […]

New technical problems at Medupi place South Africa at risk

  New technical problems arising during the commissioning of Unit 6, the first of six 800 MW generation units at Eskom’s Medupi power station, may be placing South Africa’s electricity supply at risk. These problems have made it impossible for Eskom to conduct blow-through testing of the first Hitachi boiler at Medupi at the steam […]

Further delays in first synchronisation of Unit 6 at Medupi announced by Eskom

  At its interim financial results presentation for the period 1 April to 30 September 2014, which was held on 25 November 2014, Eskom announced further delays in first synchronisation of Unit 6 (the first generation unit to be synchronised to the grid) at Medupi power station. The project team at Eskom and the minister […]

Losses put Eskom’s sustainability at risk

  Eskom predicts that it will post a net loss of R8,8-billion for the six month period from September 2014. This loss will virtually wipe out the utility’s R9,3-billion profit by 31 March 2015, undermine the utility’s capex and opex budgets, and put the utility’s sustainability at risk. Speaking at Eskom’s interim financial results presentation on […]

Delay in first synchronisation of Unit 6 at Medupi likely

  At a briefing by Eskom’s Medupi project manager, Roman Crookes, and the head of capital projects, Dan Morakane, it was indicated that a further delay in the first synchronisation of Unit 6 at Medupi power station is increasingly likely, and that the minister of Public Enterprises and other key stakeholders were being informed of […]

Medupi’s ash conveyor commissioned

  Medupi’s overland ash conveyor was successfully commissioned and operated from the DCS for the first time. The ash overland conveyor will transport the boiler bottom ash via the Unit 6 coarse ash, transverse ash and the overland link conveyor which includes the fly ash from the pulse jet fabric filter plant and ash conditioning plant, to the […]

Medupi fires up: First oil fire

  Unit 6, the first unit of the Medupi power station which is scheduled to be synchronised at the end of the year, successfully achieved its first oil fire on 17 October 2014. This is a major milestone for the project. Liquefied petroleum gas (LPG) and fuel oil were used to ignite the first oil fire.   […]

Medupi receives boiler registration

  Eskom’s Medupi power station has received its pressure equipment regulation certificate of registration for Unit 6 from the Department of Labour (DoL). Boiler registration with the DoL is required as no one may use a steam generator without such a certificate, and the boiler must be registered before energy can be applied to it and before the start of the […]